The quote that loses money is missing three lines

A day rate times a number of days is not a quote. The three lines most often left out, a worked extension example, and how to present a price a customer can compare.

Most builders can price a job in their head to within a few hundred pounds, and most of them are right about the work and wrong about the job. The work is the bricks, the boards and the days. The job is everything that has to happen around it: getting materials to a site with no parking, protecting a hallway, skipping plasterboard offcuts, waiting two hours for a building control inspector to arrive, and going back a fortnight later to snag a door that has swollen.

None of that appears when a price is built as rate × days. That is why two firms quote the same extension and one makes money.

Where a price actually comes from

A quote that survives contact with the job is built in four layers, in this order:

  1. Measured work — quantities against a labour constant, not a feeling.
  2. Preliminaries — the cost of being on site at all.
  3. Risk and waste — the part that is certain to happen but never gets measured.
  4. Margin — added to the total, not carved out of it.

Take a 24 m² single-storey rear extension, one storey, knock-through, kitchen moved, finished to a painted plaster standard. A first-pass quotation might look like this:

Layer Line Amount
Measured Groundworks, footings, slab £4,850
Measured Blockwork, openings, steel £6,200
Measured Roof structure and covering £3,400
Measured First fix, insulation, plasterboard £3,950
Measured Second fix, kitchen install, decoration £4,300
Preliminaries Scaffold, skip hire, site protection, welfare £1,750
Preliminaries Building control fees and inspection time £420
Risk 5% of measured work £1,138
Cost £26,008
Margin 17% of cost £4,421
Quoted price £30,429

The measured work is 87% of the cost and all of the customer’s attention. The other 13% is where the profit lives or dies.

The three lines that go missing

Preliminaries. Two weeks of scaffold on a house is not a rounding error, and it is not included in “labour and materials” however carefully those are counted. Neither is a skip, nor the plastic sheeting and hardboard that stops a customer’s hallway becoming the reason you are not paid the final instalment.

Waste. Ordering exactly the quantity drawn is how a job stops on a Friday afternoon. Allow a percentage per material — highest for cut-heavy work like tiles and timber, lower for sheet goods bought in whole units — and count it as a cost rather than hoping you will “use it up somewhere”.

Time that is not labour. Quoting, ordering, chasing a delivery, the two hours lost when an inspector arrives late, the return visit for a snag. On a four-week job this is routinely two days. Priced at nothing, it comes out of the margin.

Presenting it so it can be compared

A customer with three quotes is not comparing totals, because the totals are not for the same thing. Give them a page they can read line by line:

  • What is included, in the customer’s language, room by room.
  • What is excluded, named explicitly — decoration, flooring, appliance connection, making good to the drive, anything the customer is supplying.
  • What would change the price, and by roughly how much, so a variation is a conversation rather than an argument.
  • Payment terms tied to stages of the work, not to dates on a calendar.
  • How long it will take, and what depends on them — a decision on tiles, a kitchen delivery date.

The excluded list is the single most valuable box on the page. A customer who expected flooring to be included will not read the inclusions twice; they will read the exclusions, once, and either ask or accept.

Variation, retention and the final payment

Assume the price will change. Every change after the quote is either a variation with a written number, or a gift. Keep a log, however small the job, with the date, what changed, what it cost and who asked for it — and get it acknowledged the same week, while the customer still remembers asking.

On larger work, retention is normal practice: a percentage held back for a period after completion. Whatever the terms, they belong in the quote, in plain words, before the work starts. A customer discovering a retention clause at the final invoice is a customer who feels misled, and that is a dispute rather than a payment.

Where the rules touch the price

Two things change a quote beyond the arithmetic. If the work needs building regulations approval, the fees and the inspection time are real costs, and the customer will not have budgeted for them unless the quote tells them — see GOV.UK on building regulations approval. And for a domestic job, the VAT treatment follows the reverse charge rules, which change what appears on your invoice even though it does not change what the customer pays — the worked version is in the domestic reverse charge explained.

If the contract was agreed in the customer’s home rather than at your premises, they generally have a short cancellation period, and starting early requires their written agreement. Get it in writing; it costs one sentence in the quote.

The four workbooks behind this page are a quote template with those four layers built in, a job tracker, a variation log and a retention sheet — all plain Excel, no macros, so a customer’s accountant can open it and so can yours.

General information only, not tax or financial advice. Every guide links to the current GOV.UK page for the rules it applies.