Your first invoice decides how you get paid all year
Invoicing and record-keeping as a new subcontractor: what the invoice has to show, why materials need their own line, and the records that pay for themselves at the year end.
The first month of self-employment is mostly admin, and it is tempting to treat it as something to sort out later when there is money coming in. The problem is that the first invoice sets a pattern. Whatever it does or does not show is what every later invoice will do, and at the end of the year you inherit the consequences of a habit rather than a decision.
Before the first invoice
Three things need to exist, and none of them take long:
A Unique Taxpayer Reference and self-employment registered. You are registering the business, not just yourself — the tax return is the same form either way, and the date that matters is the accounting period you choose, not the day you got round to it. GOV.UK — register for Self Assessment.
CIS registration, if you are working in construction. This is separate from self-employment registration and it is the one that gets forgotten, because it is the contractor’s process and nobody tells you it is also yours. A subcontractor who is registered for CIS and has been verified by the contractor has deductions taken at 20% of the labour element. One who is not registered has 30% taken instead — a tenth of every labour pound, gone until the year end, purely because a form was not sent. The scheme itself is set out at GOV.UK — what is the Construction Industry Scheme.
A business bank account. Not legally required for a sole trader, practically required from the moment a contractor asks for payment details that differ from the name on the invoice. Mixing the two makes the year-end reconciliation a week of guesswork.
What the invoice has to carry
An invoice that a contractor’s bookkeeper can process without ringing you has, at minimum:
- your name, trading name and address, and the contractor’s
- a sequential invoice number and the invoice date
- a clear description of the work and the period it covers
- labour and materials as separate lines — the deduction is calculated on labour only, and an invoice with one “works completed” total invites the contractor to guess
- the total, and separately what was deducted and what is being paid
- your UTR and CIS registration number, so the contractor can verify you rather than defaulting
If you are VAT registered, the VAT rules for construction work between VAT-registered businesses include the domestic reverse charge, which changes the wording and the figures on the invoice. That is a separate page of its own: the domestic reverse charge explained.
A worked first month
Three weeks on a refurbishment, labour £2,400, materials £860, invoiced at the end of the month:
| Line | Amount |
|---|---|
| Labour | £2,400.00 |
| Materials | £860.00 |
| Invoice total | £3,260.00 |
| CIS deduction, 20% of £2,400 | −£480.00 |
| Paid | £2,780.00 |
If the same invoice had been raised as a single £3,260 “works” line, a contractor applying 20% to the whole thing would have deducted £652 and the difference — £172 — would have come back only after a conversation, if at all. Do the arithmetic on that for a year.
The contractor owes you a written statement showing what was paid, the materials and the deduction, within 14 days of the end of the tax month. Keep every one. They are the evidence for the claim at the year end, and reconstructing twelve months of them in April from memory is how refunds get lost — the year-end calculation walks through one.
The records that pay for themselves
Mileage. Journeys between jobs and to suppliers are a business cost, and the allowance is split at a mileage threshold — a higher rate for the first 10,000 business miles in the tax year and a lower one after. That split is why a single number in a notebook is not enough: you need date, destination, purpose and miles, per journey. Check the current rates before you use them.
Tools and equipment. Day-to-day consumables are an expense of the year. Anything with lasting value is capital, and the tax treatment differs. Keep the receipt either way, and keep a register: what it was, when it was bought, what it cost. When a tool is stolen or breaks, the register is the difference between a claim and a story.
Daily job sheets. The least glamorous document and the most useful one. Site, date, hours, what was done, who was there. They settle a disputed invoice, they support a payment dispute, and they are the raw material for pricing the next job.
The workbooks behind this page are exactly these four things — a per-line invoice, a mileage log that does the threshold split, a tool register and daily job sheets — in plain Excel, no macros.
General information only, not tax or financial advice. Every guide links to the current GOV.UK page for the rules it applies.